September 2021

Location: Gimli, Manitoba

Project Goal:

The goal is to remove and demolish old distillery tanks as new tanks were to be installed.

Scope:

This project was done for Diageo at the Crown Royal Distillery in Gimli, Manitoba. Rakowski was responsible for shearing 6 Distillery Tanks with a 100% recycle rate.

Number of Crew Involved with the Project:

1 Operator and 1 Site Manager/Safety

Duration:

4 Days to complete.

Rakowski Demolition